Energy Generation of 23,000 MW and Distribution

 

PROJECT OVERVIEW

Status:
Commenced
Implementing Ministry (MDAS):
Ministry of Energy and Petroleum
Location:
Country Wide
Sector:
Infrastructure
MTP Target:
To improve on power availability to meet industrial and domestic demand.
 

OBJECTIVE

To increase national power generation, provide the energy required to accelerate growth and mobilize private sector capital for generation of electricity from renewable energy.
 

PROJECT COMPONENTS

  • Olkaria 1 ? 140 MW Geothermal Power Project
      STATUS:
      On Schedule/Ahead of Schedule
      MTP TARGET:
      To increase access to electricity in rural areas.
      COMPONENT PROGRESS:
      • Geothermal Corporation has drilled 6 wells in Menengai.
      • The Rigs are currently on wells 5 and 6 ? Each has a potential of 10Mw.
      • Project scheduled for completion by end of 2013.
  • Olkaria II ? 35 MW Third Unit
      STATUS:
      On Schedule/Ahead of Schedule
      MTP TARGET:
      To increase access to electricity in rural areas. Kengen full commissioned 35 Mw capacity.
      ANNUAL TARGET:
      35 MW available.
      COMPONENT PROGRESS:
      Full commissioned capacity of 35MW Completed in April 2010 as scheduled.
  • Olkaria III - Additional 85 MW Geothermal Power Plan
      STATUS:
      Not Started/Behind Schedule
      MTP TARGET:
      To increase access to electricity in rural areas.
      COMPONENT PROGRESS:

  • Olkaria IV - 140 Mw Geothermal Power Plant
      STATUS:
      On Schedule/Ahead of Schedule
      MTP TARGET:
      To drill 10 production Wells. To enhancement of Power Plant by 70 Mw electricity generated. To increase access to electricity in rural areas.
      COMPONENT PROGRESS:
      Six production well have been drilled out of the target of 5.
  • Menengai 1000MW Geothermal Project, installation of well head units; and Construction of a 140Mw pow
      STATUS:
      Commenced
      COMPONENT PROGRESS:
      Geo-exploration completed.

      Construction of the plant ongoing.
  • Dongo Kundu Coal fired Plant 600 Mw
      STATUS:
      Not Started/Behind Schedule
      MTP TARGET:
      Additional 180 Mw.
      COMPONENT PROGRESS:
      A site has been identified at Shauri Moyo at the Coast Region. Implementing partner Daewoo International.
  • Kiambere Unit 1 Upgrade from 72 to 82 Mw)
      STATUS:
      On Schedule/Ahead of Schedule
      COMPONENT PROGRESS:
      The Kiambere Unit 1 upgrade from 72Mw to 82Mw was completed in October 2009 and its fully operational.
  • Tana Hydro Power Station Upgrade by 10MW to 20 MW
      STATUS:
      Not Started/Behind Schedule
  • Ngong Wind Plant ? 5 MW
      STATUS:
      On Schedule/Ahead of Schedule
      COMPONENT PROGRESS:
      The Wind Plant was completed in July 2009 and its fully operational.
  • 120 Mw Medium-Speed Diesel Plant Built at Kipevu ?
      STATUS:
      Commenced
      COMPONENT PROGRESS:
      Trial commissioning ongoing from December 2010 and the final commercial operation projected for January 2011.
  • Sangoro Hydro-Power Station ? 21Mw
      STATUS:
      On Schedule/Ahead of Schedule
      COMPONENT PROGRESS:
      Project under construction and expected date of completion was November 2011.
  • Kindaruma Unit 3 - 32 Mw. and rehabilitation
      STATUS:
      Commenced
      COMPONENT PROGRESS:
      The Power contract was signed and commenced in February 2010 and the expected completion date is June 2012 for the 3rd Unit and rehabilitation to be completed by mid 2013. Civil contract commenced in July 2010.


  • Athi River Mining Coal Power Station 19 Mw
      STATUS:
      Not Started/Behind Schedule
      MTP TARGET:
      To produce a total of 19 Mw.
      COMPONENT PROGRESS:

  • Wind Power Station Built at Lake Turkana - 300 Mw
      STATUS:
      On Schedule/Ahead of Schedule
      MTP TARGET:
      Additional 90 Mw available.
      COMPONENT PROGRESS:
      Project preparation ongoing. Power Purchase Agreement (PPA) negotiations approved by ERC and signed in January 2010.

      300Mws from 365 turbines in Lake Turkana starts in June 2012 to be completed in 2015.
  • Ngong I Wind Phase II ? 6.8MW
      STATUS:
      Not Started/Behind Schedule
  • Ngong II Wind ? 13.6 MW
      STATUS:
      Not Started/Behind Schedule
  • Eburu 2.3 MW Geothermal
      STATUS:
      Not Started/Behind Schedule
  • Wellhead Generators
      STATUS:
      Not Started/Behind Schedule
  • Rural Electrification Programme
      STATUS:
      On Schedule/Ahead of Schedule
      LOCATION:
      Nationwide
      COMPONENT PROGRESS:
      During Phase 1: 2008-2012 the following are the facilities that were connected;

      Trading Centres;  9,415

      Public Secondary Schools;  6,647

      Health Centres; 3,276

      This has increased connectivity from 12% to 22%.

      During Phase 2 the Authority is targeting to increase the national connectivity from 22% to 65%.
 