Objective: To maintain existing road network and airstrips Computerized Information Maintenance Management Systems
This strategy will lead to the construction of 1,327 km of roads through periodic maintenance (9 billion); reconstruction and rehabilitation of 1,364 km of failed roads sections at a cost of Kshs 55 billion and the resuscitation of 40 sealing camps and resealing units at Kshs 2 billion. In addition, a road maintenance manual will be developed. The upgrading of 12 existing weighbridges and the establishment of 15 mobile weighbridges and 4 weigh–in – motion (WIM) will cost approximately Kshs.6 billion. In addition, the management of road axle load controls will be prioritised as well as the routine maintenance of airstrips.